Reopening of Ballina-Birdhill road this Friday
There was great delight throughout the district last weekend at the announcement that the R494 is scheduled to re-open on this Friday, May 3.
Please note the following update on R494 upgrade and Killaloe Bypass:
R494: Section 1 (Roolagh Roundabout) – Lifting of beams at East Abutment of STO1; demobilisation of crane has commenced; Stop & Go in place to remove sections of jib.
Section 2 (Roolagh to Equestrian Centre) – New Traffic Management plan in place from May 3.
Sections 6/7 – Both sections will open to two-way traffic from Friday, May 3.
Killaloe Bypass/Bridge Crossing:
Kincora Roundabout: manned plant crossing during work hours for plant entering works area. Traffic management to swap to southbound lane until May 20.
Clarisford Road: Temporary diversion to facilitate earthworks will be in place from Wednesday, May 1.